State and local officials said
the town is not in serious jeopardy
of losing state building aid for
the new high school after voters
rejected a second access road required
under the state fire code.
In order to receive financial
aid from the state for the construction
of a new school, the
structure’s plans must be approved
and the building must
meet fire codes, both at the local
and state level. With the recent
rejection of a proposal to construct
a $1.25 million secondary
access road to the future high
school, required by Fire Chief
Tom McPherson for the school to
open, some worry that the state
may rescind funding for the construction
project.
State aid would cover 30 percent
of the cost to build the new
high school, roughly $17 million
of the $55 million project.
“If you don’t build by the
code, you don’t get the money,”
said Selectman Charles McMahon.
“It’s the view of the people
in Windham who have not accepted
that there is a higher jurisdiction
and the state Department
of Education that clearly states in
their codes and their rules what
it takes to build this high school.
We need to respond to that, not
with opinion, but with statements
of fact.”
In an e-mail sent to town officials,
Ed Murdough, of the
New Hampshire Department of
Education, reiterated state fire
codes must be met in order for
the town to receive building aid.
Chief McPherson, who has publicly
stated he will not allow the
school to open without a second
exit, has the authority to enforce
the code if in “his judgment there
is a likelihood that the primary
access could be blocked during
an emergency situation,” according
to Murdough.
According to Murdough,
the only scenario in which the
school would lose state funding
would be if the building never
opened, an outcome he called
“not realistic.”
“My expectation is that
they’re going to work it out,”
he said. “How they work it out,
I don’t know, but they’ve got to
resolve that locally.”
In the meantime, McMahon
has proposed a meeting between
state and local authorities
to hash out the problem
and determine a solution on
Sept. 29.
“It’s in law, it’s irrefutable, and
sadly, there are those that don’t
except that. I don’t want to mortgage
our future and children’s
safety on opinion,” McMahon
said. “Let’s get the authorities in
the same room.”
According to McMahon,
close to eight months would be
needed to construct a second access
road, leaving the town with
a tight schedule to fulfill the requirements
to ensure the school
opens on time next fall. McMahon
said that the rapidly closing
window of time to resolve the
issue had spurred the board to
get involved in finding a viable
solution.
“We have to sit down and just
meet with everybody involved
and try and resolve this,” said
Selectman Roger Hohenberger.
“I can’t foresee an instance
where the school can open and
we won’t get 30 percent state aid.
I can’t foresee an instance where
the school won’t open.”