BY
JENN McDOWELL
The Windham Board of Selectmen
has about a week left to
decide whether a utilities conduit
should be installed under Interstate
93 by the weigh station.
The state plans to start the
Windham portion of the largescale
I-93 widening this summer,
and needs to know whether the
conduit will go in before getting
too deeply into the improvements.
The conduit would include
phone, cable and electricity lines,
and a water pipe as well as fiber
optics line for future developments,
said highway agent Jack
McCartney at the board’s last
meeting on Monday, July 14. It
would serve the Wall Street area
by Route 111, providing the potential
for future development of
that area.
“In the infant states of doing
the work on the (Route) 111 bypass,
this item was brought up
and fell on deaf ears,” said Vice
Chairman Bruce Breton. “The
question is, do we need this for
the viability of Windham in the
future, and the answer is yes.”
Chairman Dennis Senibaldi
said the state has agreed to pick
up the cost of installing the conduit
as part of their improvements
and would add the conduit work
into plans before going out to bid
on the Windham portion of the
project. The town would pay for
the cost of the piping and other
materials, he said.
“Just to say whether we want
it or not gives them the opportunity
to put it in their bid package,”
Senibaldi said.
McCartney said the I-93 construction
provides an ideal opportunity
to install the utilities
and attract developers to the Wall
Street area.
If the town waits any longer, it
will be much more difficult and
costly to dig up the highway and
install the conduit later, he said.
The cost of materials will likely
go up as time goes by, he said.
“A lot of the trench work
is going to be done in current
construction. For the conduit,
you just take some glue and put
the pieces together,” McCartney
said. “I don’t see it being ridiculous
numbers.”
A sewer line that would serve
the Wall Street area is also on
the table, but can be worked
around the widening project and
wouldn’t need to be installed until
much further down the road.
McCartney reiterated that
the utilities are not a need at this
point, but would simply be installed
for the future viability of
development in Windham.
Selectman Roger Hohenberger
said he wanted more information
regarding the town’s
financial liability for the conduit
before making a decision.
“If it’s only an X amount of
dollars and now’s the right time
to do it, that might prompt a different
decision,” said Hohenberger,
adding the conduit discussion
goes back 30 years and the town
has not had a pressing need for
the added utilities yet.
The board requested that Mc-
Cartney put some cost estimates
together and meet with them
again on Monday, July 21.
“In my opinion, if the services
are available ... we could attract
development in the Wall Street
area,” McCartney told the board.
Selectman Charles McMahon
said the conduit discussion
has been ongoing for decades,
and it’s time for the town to follow
through.
“There’s the potential now to
at least do something for Windham’s
future,” he said. “We really
ought to make this happen.
So many things have changed
in now in our town. The future
folks said wouldn’t happen has
happened.”