By Ryan O’Connor
Staff Writer
A $1 million donation Eugene and Anne Slusser to build a new
senior center in Hopkinton may not be enough after the initial bid on
the project came in nearly 50 percent higher than expected.
Milstone Engineering and Construction of Concord, the company
handpicked by the town for the project, submitted a $1.45 million
estimate to build the center, which will be placed at Houston Fields
next to the Hopkinton Library.
Don Lane, the selectmen’s representative and chairman of the
Slusser Center Committee, said the estimate is not reasonable from his
and other officials’ perspectives, but the two sides are re-evaluating
the cost of the project.
“We’ve been working on it and we’ve chopped about $250,000 so
far. We’re not finished yet,” Lane said. “We’re bringing it more and
more into line every day.”
Among the items the town may be looking to cut are some
energy-efficient options discussed at two public hearings during the
summer, including spray-in insulation, a modern heating and
air-conditioning system, low-energy glass, light sensors and a dimming
feature to automatically adjust indoor lighting with natural light from
outside.
According to Town Administrator Ed Wojnowski, those items will
cost 3 percent more up front, but may save the town a one-third of the
building’s energy costs down the road.
Still, Lane said, the town will make cuts where appropriate to make the cost reasonable.
“We’ll still look at those types of (energy-efficient) things,
but we have to be responsible about it. If it’s going to cost
considerably more than we have to spend, then we won’t,” Lane said. “We
may pick and choose between some of those things and we certainly want
to build as green a building as we can, but still use common sense
because we don’t have the money to experiment.”
Should the cost still exceed $1 million, officials will not ask the town for extra money, said Lane.
“We’re going to start fundraising in November to try to make up
the difference and also encourage people to donate various items that
can be used at the center,” Lane said. “I’m pretty confident we will be
able to get it done. This town has been very supportive of practically
everything like this in the past.”
The only cost to Hopkinton, once the senior center is open,
will be for maintenance and operations, which will run about $28,000 to
$35,000 per year, Lane said.
“We aren’t adding any key personnel, which would impact that
cost considerably,” he said. “We’re moving people around, like the
social services director and recreation director, who will both be
operating out of that building, which eliminates the need to add
another person.”
Robert Mattes, the town recreation director, has been in charge
of the facility since Columbia Hall was closed as a community center
last month.
In addition, the two-story Slusser Center will house the town’s
human services office, food pantry and Dial-a-Ride desk, among other
services.
The town recreation offices will remain at Columbia Hall.
Construction on the new 7,344-sqaure-foot building is set to
begin this month and, although slightly delayed, Lane expects the
timetable will be close to the original plan.
“We’re still moving ahead and still planning on an April
opening for it,” he said. “That’s our target and were not going to miss
it by much.”